Projects

Indian Creek Station Rehabilitation

Current Status: Construction

RIDER ALERT:

indian-creek-banner

On Sunday and Monday, Dec. 8-9, 2024, rail service at Indian Creek will be temporarily suspended for the installation of a new pedestrian bridge. Shuttle and Mobility service will connect customers to the Blue Line at Kensington Station. Please allow at least 15 extra minutes for your trip if taking the shuttle.  Customers who drive should consider parking at Kensington instead 
(Google Maps directions here).                                                              

Shuttle and Mobility bus boarding locations on Dec: 8-9:

  • Indian Creek to Kensington (westbound): Kiss & Ride in eastern parking lot at Indian Creek
  • Kensington to Indian Creek (eastbound): Kiss & Ride outside west faregates at Kensington. 

Local bus service is unchanged. MARTA Routes 24, 107, 111, 116, 119, and Ride Gwinnett 70 will continue to serve Indian Creek as scheduled. Route 107 is temporarily boarding at the eastern Kiss & Ride. 

We Value Your Feedback 

We appreciate your patience and welcome your feedback during this renovation.  Please help us improve future project by taking this brief survey. 

Indian Creek Survey - English

Indian Creek Survey - Español

indiancreek2

Image description: The image above shows a design rendering of the future pedestrian bridge connecting Indian Creek MARTA Station to the community to the north. The bridge extends from the station entrance at the upper right across to the lower left.  

Overview:  

MARTA is renovating Indian Creek Station as part of its State of Good Repair program. The most exciting new feature will be a pedestrian bridge that crosses over the tracks and connects to Durham Park Road on the north side of the station. There will also be extensive upgrades to the platform, concourse, walls, furniture, elevator, lighting, public artwork, landscaping, as well as deep cleaning. The projected timeline for completion of the pedestrian bridge is April 2025, and the entire renovation project’s projected completion is is Spring 2025. 

Project Features   

  • A new Pedestrian Bridge for access from Durham Park Road 
  • New lighting and illuminated signage at the platform, plaza, and concourse levels
  • New wall paneling, metal doors, and door frames
  • New landscaping, trash receptacles, and benches
  • Pressure cleaning throughout the station 
  • New copper gutter system 
  • Repairing and refinishing the existing wood barrel ceiling
  • New concrete at the platform, plaza, and concourse levels 
  • New SMART Restroom for customers, which use technology to keep the facilities safe and maintained. 
  • New operator restroom on the platform level 
  • New paving of the parking lot and bus loop, and redesigning for better traffic flow 
  • New roof and wall paneling on the Police Precinct and the Traction Power Substation (TPSS) Building
  • Repair of the windscreens at the platform level 
  • New artwork

new-ramp

Image Description: The image above shows a new wheelchair-accessible ramp completed at the east bus loop at Indian Creek Station. 

Image description: The image above shows a design rendering of ongoing renovations to the exterior entrance for Indian Creek MARTA station. A concrete plaza is in the foreground, with multiple people walking and sitting outside. A new public artwork stands in the center.

Stay Informed

Sign up for email updates!   

Contact:

Please submit comments regarding the project via mail or email to: 
Romon Moultrie, MARTA Project Manager 
rmoultrie@itsmarta.com 
(404) 848-6647